Project Description

The Project includes construction, operation and transfer of Ankara – Niğde Motorway on a BOT basis and consists of;

  • Ankara – Acıkuyu,
  • Acıkuyu – Alayhan and
  • Alayhan – Gölcük intersections.

After a competitive bidding procedure on 14 April 2017 ERG Otoyol Yatırım ve İşletme A.Ş. has been awarded the BOT type of Ankara – Niğde Motorway project with a concession peiod of 11 yeras 10 months and 17 days including the 3 year investment period with a total investment cost of 4,031,055,531 Turkish Liras (1,033,603,982 Euros).

 

The Ankara – Niğde Motorway Project consists of 3 main sections :

Part No
Part Name
Length (km)
Main Route Connection Roads Total
1 Ankara  Gölbaşı – Acıkuyu Intersection 105,41 12,20 117,61
2 Acıkuyu Kavşağı – Alayhan Intersection 112,75 34,46 147,21
3 Alayhan Kavşağı – Gölcük Intersection 56,72 2,23 58,95
Project Route
274,88 48,89 323,77

We are Connecting North with South